This bridge design was completed in the winter of 2012 by the RJM Engineering Company. This project sold on May 8, 2014 and RC Construction Company of Cutler, Ohio was the low bidder with a bid of $561,290.60. The contractor began construction in August 2014 and completed the bridge on November 1, 2014. The existing steel truss bridge was replaced with a non-composite pre-stressed box beam bridge.