This 2018 Baker Road bridge replacement was surveyed, designed and built by the ACEO- the piling, prestressed concrete beams, paving and guardrail were contracted out   A steel beam bridge was replaced with a prestressed concrete box beam bridge.  The total construction cost was $224,074, $42,000 of that was funded through a Transportation Improvement District Grant.