CR 48- New England Road Bridge Replacement
Rome Township's 2016 New England Road bridge replacement was surveyed, designed and built by ACEO. Crews modified the existing abutments ...
TR 225- Dover Township Hamley Run Road Bridge Replacement
Dover Township's Hamley Run Road bridge Replacement was surveyed, designed and built by the ACEO. Surveyed, Designed, and built by ...
TR 265- Waterloo Township Hamley Run Road Bridge Replacement
Waterloo Township's Hamley Run Road bridge replacement was surveyed, site planned and ROW planned by ACEO and constructed by DGM ...
CR 20- East Scatter Ridge Road Paving Project
In September 2016, Nuko Paving began a 3 mile asphalt paving project on East Scatter Ridge Road. The project consisted ...
CR 73- Wolfe Bennett Pavement Project
In November 2016, Shelly and Sands began a pavement project on Wolfe Bennett Road that consisted of 1.02 miles of ...
CR 1A- Happy Hollow Road Paving Project
In August 2016, a 5 mile motor paving/chip and seal project began on Happy Hollow Road. This was the first ...
CR 75- Coolville Ridge Road Slip Repair
Construction of a second slip repair project on Coolville Ridge Road began in September 2016. The Alan Stone company was ...