CR 20- Strouds Run Road Slip Repair Part 2

  • Before construction
  • After construction

This project was part 2 of the ATH-CR20/VAR Landslide Repairs Project.   The project was located on CR 20 just south of the intersection of Canaan TR 215 (Scatter Ridge Road).  This was a 72′ long drilled shaft pier call surveyed and designed by Donnie Stevens, the assistant engineer.  A FHWA (Federal Highway Administration) Emergency Grant paid for 80% of the construction cost.

CR 44- Bucks Lake Road Rock Channel Protection

  • Slope reconstruction in process
  • After construction
  • After construction

A slip developed on CR 44- Buck’s Lake Road, adjacent to the Middle Branch of the Shade River.  The method of repair was to construct a rock toe at the base of the slope and build a rock fill.  This solution both stabilized the slope and provided erosion control along the river bank.  All work was performed by Athens County Engineer employees.  CR 44 is classified as a “Federal Aid Route”, so the source of funding was the Federal Highway Administration (FHWA) Emergency Funding.  FHWA paid 80% reimbursement of the construction cost or $35,855 to the Athens County Engineer’s Office.

Office Closed to The Public

The safety and health of our employees and customers is the top priority of County Engineer Jeff Maiden.  The office will be closed to public access starting Monday, March 16th, until the COVID-19 public health crisis is over.

THE BUSINESS OF THE OFFICE WILL CONTINUE by email and telephone.  Land Surveyors may submit surveys to Brandon Williams and/or Donnie Stevens for closure check and review via email at the following:

bwilliams@athensoh.org

dstevens@athensoh.org

 

Surveys that comply will be stamped, signed, and returned via email.

CR 24- Harmony Road Slip Repair

  • Before construction- slip is to the edge of the road
  • After construction- slope reconstuction method

The following three 2018 featured slip repairs were a result of severe storms and flooding rains during late February/early March of 2017.  This slip, located on Harmony Road, was approximately 34 feet long and produced damage to a 40 ft long culvert.  The slope reconstruction method (325 CY of rock) was used to repair this slip with a total project cost of $85,298.

 

CR 75- Coolville Ridge Road Slip Repair

  • Before Construction
  • After Construction

As a result of severe storms and flooding rains during late February/early March 2017, Coolville Ridge Road developed a roadway slip that resulted in road surface loss, pavement depressions along the north bound lane and a slope failure to the northeastern side of the roadway.  The drilled shaft wall was constructed by the Alan Stone Company with a total project cost of $136,398, 75% of which was reimbursed by OEMA.

CR 37- Concord Church Road Slip Repair

  • Before Construction
  • Before Construction
  • After Construction

As a result of severe storms and flooding rains during late February/early March 2017, Concord Church Road experienced a roadway slip that resulted in road surface loss, pavement depressions along the eastbound lane and slope failure to the north side of the roadway.  This slip repair was surveyed and designed by ACEO staff and constructed by the Alan Stone Company.  The total construction cost was $91,439, 75% of which was reimbursed by OEMA.

CR 15- Wood Road Bridge Replacement

  • Before

The Wood Road bridge replacement project consisted of the installation of a 8′ x 4′ precast box culvert by Lindsay Precast and 100 LF guardrail by PDK construction.  The total construction cost was $116,929.

CR 10- Baker Road Bridge Replacement

  • Before Construction
  • Construction
  • Finished Bridge
  • Finished Bridge

This 2018 Baker Road bridge replacement was surveyed, designed and built by the ACEO- the piling, prestressed concrete beams, paving and guardrail were contracted out   A steel beam bridge was replaced with a prestressed concrete box beam bridge.  The total construction cost was $224,074, $42,000 of that was funded through a Transportation Improvement District Grant.

CR 73- Wolfe Bennett Road Motor Paving Project

  • Motor Paving
  • Chip and Sealing
  • Finished Product

Wolfe Bennett Road was paved using federal funding from the Eastern Federal Lands Access Program (EFLAP) with 20% local funds.  Construction Cost = $304,167 for 3.5 miles paving.

CR 1- Kimberly Road Paving Project

  • Crews Laying Asphalt
  • Crews Rolling Freshly Laid Asphalt

In 2018, Kimberly Road was paved using funds from a RUMA Settlement with American Electric Power.  Construction Cost = $245,271 for 2.6 miles paving.