2019 Projects

2019 Projects


CR 36-3.63 Hooper Ridge Road Slip Repair Progression

This slip on Hooper Ridge Road  at the 3.63 mile marker was caused by the storms in February 2018 that ...

CR 75- Coolville Ridge Road Slip Repair

In late July 2019 the Alan Stone Company began a slip repair on County Road 75- Coolville Ridge Road. This ...

CR 109- Beebe Road Slip Repair

In mid-July 2019 Shelly and Sands, Inc. began work on two slip repairs on County Road 109- Beebe Road. This ...

CR 34- Dutch Creek Road Slip Repair

In mid-May 2019 the county contracted out four slip repairs to the Alan Stone Company, two on Dutch Creek Road ...

CR 87- Antle Orchard Road Slip Repair

In late February 2019 the Alan Stone Company began work on a slip repair project at the 0.09 mile marker ...

CR 30- Hocking Parkway Slip Repair

In February 2019 the Alan Stone Company began work on a slip repair on County Road 30- Hocking Parkway. This ...

TR 181-1.00 Wildman Road Bridge Repair

The Athens County Engineer is responsible for bridges on township roads of 10’ span or longer. This Troy Township bridge ...

CR 73- Wolfe Bennett Road Bridge Replacement

In mid-August 2019 county crews began work on County Road 73- Wolfe Bennett Road bridge replacement. Lindsay Precast designed and ...

TR 27- Gun Club Road Bridge Replacement

In June 2019 county crews began work on a bridge replacement on Waterloo Township’s Gun Club Road. The 10’ x ...

CR 9- Salem Road Bridge Replacement

In early May 2019 county crews began work on a bridge replacement on Salem Road.  The 8’ x 4’ precast ...

TR 181-0.25 Wildman Road Bridge Replacement

In mid-April 2019 county crews began work on a box culvert replacement project on Wildman Road in Troy Township.  The ...

CR 34- Mush Run Road Bridge Replacement

In late March 2019, county crews began work on a box culvert on County Road 34- Mush Run Road.  Scioto ...